CapacityVerified End-2025
446 MW installed renewable capacity
The verified operational renewable capacity is 446 MW. The commonly cited 880 MW figure includes announced and under-construction projects that have not yet reached commercial operation.
- Solar PV: ~420 MW operational
- Wind: ~26 MW operational
- Other (hydro, biomass): negligible
PipelineUnder Construction
2.6 GW under construction; 1.48 GW by August 2026
Algeria has 2.6 GW of renewable capacity under active construction. A 1.48 GW tranche is scheduled to commission by August 2026.
- Major sites: Hauts Plateaux, Sahara, and coastal provinces.
- Primary EPCs: Chinese consortia (SEPCO, CMEC) with local partners.
- Grid integration is the critical path risk.
TariffFIT
Corrected FIT: 15.94 DZD/kWh for 1–5 MW solar
Feed-in tariff for 1–5 MW solar PV projects is 15.94 DZD/kWh. Larger projects negotiate through bilateral utility agreements. The tariff is viable for distributed solar but marginal for utility-scale without concessional financing.
- 1–5 MW: 15.94 DZD/kWh (fixed FIT)
- 5–50 MW: negotiated tariff, typically 12–14 DZD/kWh
- >50 MW / IPP: bilateral PPA with Sonelgaz
HydrogenSoutH2 Corridor
Hydrogen target: ~40 TWh/year by 2040
Algeria's green hydrogen target is approximately 40 TWh/year of renewable hydrogen production by 2040, primarily for export to Europe via the SoutH2 Corridor.
- First major asset: $972M Chinese-built integrated facility.
- Export route: pipeline via Tunisia to Italy.
- Regulatory framework for hydrogen IPPs does not yet exist.
RegulationLaw 11-24
Foreign ownership caps and regulatory timeline
Law 11-24 governs renewable energy development. Foreign ownership is capped; Algerian majority partners are required in most configurations.
- Foreign ownership cap: 49% in generation assets.
- Permitting layers: Sonelgaz, Ministry of Energy, provincial authorities.
- Grid connection studies: 12–18 months typical.
Targets2035
15 GW renewable target and $23B investment gap
Algeria's official target is 15 GW of renewable capacity by 2035. Closing the gap from 446 MW to 15 GW requires approximately $23 billion in investment, or roughly $1.7 billion per year.
- Current investment rate is ~$400M/year; acceleration factor of 4x needed.
- Domestic financing is constrained; foreign capital requires JV structures.
- Execution risk is higher than funding risk.